Construction draw schedule calculator

Turn a contract price into draw amounts by construction phase, with each draw as a percentage, a dollar figure and a running total that ends at exactly 100 percent.

Payment schedule by construction phase

Pick the rulebook that governs the contract, enter the price, and the table below shows what becomes payable at each phase, what the running total reaches, and how much of the build the contractor is still funding.

Rulebook for the schedule

First installment after excavation starts

The closing draw is not typed in. It takes whatever the four draws above leave, which is how the column lands on the contract price.

Stages, shares and amounts

Contract price $480,000 · draws before completion 88% · closing draw 12% = $57,600

Contract price $480,000 · first installment 30% = $144,000 · remaining sum $336,000 · shared out over the later stages

German developer schedule under MaBV
StageShareAmountRunning total
Start of excavation30% of the contract price30%$144,000$144,000
Structural shell complete, including carpentry · Roof surfaces and gutters48% of the remaining sum33.6%$161,280$305,280
Heating rough-in – Windows installed and glazed19% of the remaining sum13.3%$63,840$369,120
Interior plaster · Screed · Bathroom tiling13% of the remaining sum9.1%$43,680$412,800
Ready for occupancy, against handover of possession12% of the remaining sum8.4%$40,320$453,120
Facade work3% of the remaining sum2.1%$10,080$463,200
Full completion5% of the remaining sum3.5%$16,800$480,000
Total100%$480,000

Percentages fixed by § 3 Absatz 2 MaBV, Germany.

US lender draw schedule
StageShareAmountRunning total
Site work and foundation20%$96,000$96,000
Framing and dried-in roof25%$120,000$216,000
Mechanical, electrical and plumbing rough-in18%$86,400$302,400
Insulation, drywall and interior finishes25%$120,000$422,400
Final completion and punch list12%$57,600$480,000
Total100%$480,000

Ranges typical for US construction lenders, agreed in the contract rather than set by statute.

Contract price $480,000 · deposit 3% = $14,400 · first payment 12% · balance at handover 5%

French CCMI schedule under article R231-7
StageShareAmountRunning total
Deposit held at signature3%$14,400$14,400
Site opened12%$57,600$72,000
Foundations complete10%$48,000$120,000
Walls complete15%$72,000$192,000
Weathertight roof20%$96,000$288,000
Partitions complete and building sealed15%$72,000$360,000
Fittings, plumbing, joinery and heating complete20%$96,000$456,000
Handover of the finished house5%$24,000$480,000
Total100%$480,000

Cumulative ceilings fixed by article R231-7 of the French code de la construction et de l’habitation.

How each amount is derived

Amount = contract price × cumulative share, rounded to cents. Each row is that figure minus the row above it.

The closing row carries the balance, so the money column totals the contract price and the share column totals 100 %.

Questions about Construction draw schedule calculator

How many draws does a residential construction loan usually have?

Most single-family construction loans run four to six draws, keyed to foundation, framing and dry-in, rough-in, finishes and final completion. More draws mean smaller gaps in cash flow and more inspections; fewer draws mean fewer inspection fees and a longer stretch of the job financed by the builder.

Can a builder ask for a large deposit before work starts?

State law decides. Several states cap the deposit on a residential contract, and lender-financed builds usually release nothing until the first inspection. A schedule that puts 30 percent before any work is visible will be questioned by the lender and, in some states, is not enforceable.

What happens if the draws do not add up to 100 percent?

The gap lands on the builder. If the schedule totals 97 percent, three percent of the contract price has no milestone attached and no clear moment when it becomes payable. This calculator derives the final draw from the earlier ones so the total closes exactly, and flags the entry when the earlier draws already exceed the price.

Does a draw schedule replace an AIA G702 application for payment?

No. The draw schedule sets what each phase is worth; G702 and its G703 continuation sheet report what was actually completed and stored in the current period. The schedule is agreed once at contract signing, the application is filed every billing cycle against it.

Use the calculation with your own project data

Request a trial period and tell us which workflow you want to test. We prepare Home Builder Software around that part of your work without fixing a term before we know the scope.